CAPM Readiness

Time limit: 0

Assessment Summary

0 of 161 Questions completed

Questions:

Information

You have already completed the assessment before. Hence you can not start it again.

Assessment is loading…

You must sign in or sign up to start the assessment.

You must first complete the following:

Results

Assessment complete. Results are being recorded.

Results

0 of 161 Questions answered correctly

Your time:

Time has elapsed

You have reached 0 of 0 point(s), (0)

Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)

Categories

  1. Not categorized 0%
  • Back To Practice

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
  6. 6
  7. 7
  8. 8
  9. 9
  10. 10
  11. 11
  12. 12
  13. 13
  14. 14
  15. 15
  16. 16
  17. 17
  18. 18
  19. 19
  20. 20
  21. 21
  22. 22
  23. 23
  24. 24
  25. 25
  26. 26
  27. 27
  28. 28
  29. 29
  30. 30
  31. 31
  32. 32
  33. 33
  34. 34
  35. 35
  36. 36
  37. 37
  38. 38
  39. 39
  40. 40
  41. 41
  42. 42
  43. 43
  44. 44
  45. 45
  46. 46
  47. 47
  48. 48
  49. 49
  50. 50
  51. 51
  52. 52
  53. 53
  54. 54
  55. 55
  56. 56
  57. 57
  58. 58
  59. 59
  60. 60
  61. 61
  62. 62
  63. 63
  64. 64
  65. 65
  66. 66
  67. 67
  68. 68
  69. 69
  70. 70
  71. 71
  72. 72
  73. 73
  74. 74
  75. 75
  76. 76
  77. 77
  78. 78
  79. 79
  80. 80
  81. 81
  82. 82
  83. 83
  84. 84
  85. 85
  86. 86
  87. 87
  88. 88
  89. 89
  90. 90
  91. 91
  92. 92
  93. 93
  94. 94
  95. 95
  96. 96
  97. 97
  98. 98
  99. 99
  100. 100
  101. 101
  102. 102
  103. 103
  104. 104
  105. 105
  106. 106
  107. 107
  108. 108
  109. 109
  110. 110
  111. 111
  112. 112
  113. 113
  114. 114
  115. 115
  116. 116
  117. 117
  118. 118
  119. 119
  120. 120
  121. 121
  122. 122
  123. 123
  124. 124
  125. 125
  126. 126
  127. 127
  128. 128
  129. 129
  130. 130
  131. 131
  132. 132
  133. 133
  134. 134
  135. 135
  136. 136
  137. 137
  138. 138
  139. 139
  140. 140
  141. 141
  142. 142
  143. 143
  144. 144
  145. 145
  146. 146
  147. 147
  148. 148
  149. 149
  150. 150
  151. 151
  152. 152
  153. 153
  154. 154
  155. 155
  156. 156
  157. 157
  158. 158
  159. 159
  160. 160
  161. 161
  1. Current
  2. Review
  3. Answered
  4. Correct
  5. Incorrect
  1. Question 1 of 161
    1. Question

    1. During product validation, a key stakeholder refused to sign off on the acceptance document, stating that certain functionalities did not meet their expectations. What could the project manager have done to prevent this situation?

  2. Question 2 of 161
    2. Question

    2. Which of the following documents does the project manager need to develop the project charter? (Select three)

  3. Question 3 of 161
    3. Question

    3. A project manager is leading a project that consists of four phases. Which meeting should the project manager hold at each phase to ensure the stakeholders’ continuous commitment?

  4. Question 4 of 161
    4. Question

    4. While overseeing the execution of an industrial project, a project manager observes that two stakeholders are frequently in disagreement, potentially affecting the project negatively. Which of the following options should be used to record and track this type of situation?

  5. Question 5 of 161
    5. Question

    5. Activities that involve ongoing, routine tasks designed to maintain and support the organization’s infrastructure and processes are most likely referred to as ________.

  6. Question 6 of 161
    6. Question

    6. A project team is reluctant to begin work on a project because key stakeholders may request proper authorization and clearly defined objectives before proceeding. What should the project manager do?

  7. Question 7 of 161
    7. Question

    7. Upon delivering a rebranding project, the sponsor, as well as other key stakeholders, are hesitant to accept deliverables and close the project. What should the project manager do? (Select three)

  8. Question 8 of 161
    8. Question

    8. All of the following statements are true, except:

  9. Question 9 of 161
    9. Question

    9. What are the interpersonal skills of a project manager? (select three)

  10. Question 10 of 161
    10. Question

    10. A project manager is working on a contract. After completing the contract and closing the project, she finds herself without work. What type of organizational structure does the project manager work in?

  11. Question 11 of 161
    11. Question

    11. You are managing six projects at the same time within the company. Two projects are of a similar type, while the other four are completely different. You work as a ______________.

  12. Question 12 of 161
    12. Question

    12. During the kick-off meeting of their first project, the project manager presents the project plan to stakeholders. As they go through the details, a stakeholder expressed frustration with the plan’s inaccuracies in reflecting their expectations. What is the most likely reason behind the project manager’s inaccurate description of stakeholder requirements?

  13. Question 13 of 161
    13. Question

    13. A project involves numerous stakeholders due to its multiple phases and various tasks to execute. What should the project manager do?

  14. Question 14 of 161
    14. Question

    14. The project sponsor informed the project manager that if the project costs exceed $350,000 by the end of the year, the project will receive no further funding. This is an example of which of the following?

  15. Question 15 of 161
    15. Question

    15. During the planning phase, the project manager assumed that the composition of the project’s steering committee would remain the same. But, since any change could be very critical to the project, the project manager assigned a team member to monitor potential triggers. Where should the name of the person responsible for monitoring the steering committee be documented?

  16. Question 16 of 161
    16. Question

    16. Mid-execution, a sponsor requests from the project manager to terminate the project. What should the project manager do?

  17. Question 17 of 161
    17. Question

    17. The project team will hold a monthly status review meeting with the product owner to review post-iteration deliverables. What’s the best communication type to use in a status review meeting?

  18. Question 18 of 161
    18. Question

    18. What is considered as an enterprise environmental factor?

  19. Question 19 of 161
    19. Question

    19. Which technique involves prioritizing features, epics, or user stories by business value in a sequential manner?

  20. Question 20 of 161
    20. Question

    20. In which scenario would you use a Use Case Diagram over a Story Map?

  21. Question 21 of 161
    21. Question

    21. Industries, such as infrastructure, aerospace, and automotive, use ________________ for directional alignment and integration of component activities. The success of these initiatives is measured by the realization of intended benefits and the efficiency of delivering those benefits.

  22. Question 22 of 161
    22. Question

    22. Which of the following best describes the “Project Life Cycle”?

  23. Question 23 of 161
    23. Question

    23. Which of the following is NOT considered a characteristic of a high-performing project team?

  24. Question 24 of 161
    24. Question

    24. How should a project manager promote resilience within the project team?

  25. Question 25 of 161
    25. Question

    25. A project manager is conducting stakeholder analysis using the power/interest grid below. What actions correspond to the quadrants A, B, C, and D respectively?

  26. Question 26 of 161
    26. Question

    26. The person who is motivating and influencing the project team toward a common goal is best defined as a(n) ________.

  27. Question 27 of 161
    27. Question

    27. The project sponsor expressed concerns to the project manager about whether the resulting product will meet business needs. Therefore, the project sponsor is looking to keep costs to a minimum. What should the project manager do?

  28. Question 28 of 161
    28. Question

    28. A project manager determines viable options and provides recommendations about the investment efficiency of two potential projects by implementing valuation techniques. Knowing that the discount rate is unknown, what should the project manager do?

  29. Question 29 of 161
    29. Question

    29. An organization is considering two potential projects with identical payback periods. After conducting a benefit measurement analysis, the project manager discovers that project B has a higher Internal Rate of Return (IRR) than Project A. Which project should the organization select?

  30. Question 30 of 161
    30. Question

    30. The customer sends the project manager a document outlining the new project’s requirements. While checking the document, the project manager struggles to understand some of the requirements, outputs, and especially the ultimate goal of the project. What should the project manager do next?

  31. Question 31 of 161
    31. Question

    31. To guide the development team on what they intend to achieve, a product owner provides a table that includes the key deliverables of each quarter of the 9-month project. What artifact does this table represent?

  32. Question 32 of 161
    32. Question

    32. A business analyst is eager to implement a new solution for the company. The stakeholders requested an assessment of the business value it will bring. What should the business analyst do?

  33. Question 33 of 161
    33. Question

    33. The project team finds out that several implemented features deviate from what is specified in the scope statement. Which document should the project manager consult to address the issue?

  34. Question 34 of 161
    34. Question

    34. To validate requirements, a business analyst used a technique illustrated by the following graph. What technique did the business analyst use?

  35. Question 35 of 161
    35. Question

    35. A project team is actively working on creating a solution and preparing it for delivery to the business. In which phase of the project would this activity take place?

  36. Question 36 of 161
    36. Question

    36. An organization has appointed a new project manager to replace the one who recently left. What should the new project manager do first?

  37. Question 37 of 161
    37. Question

    37. A Business Analyst is tasked with developing a product roadmap for the upcoming project. What technique should the Business Analyst choose to develop the roadmap in order to ensure it effectively captures the sequence and prioritization of user stories?

  38. Question 38 of 161
    38. Question

    38. All stakeholders are attending a meeting to discuss a new project that is expected to start within a month and to last for at least 10 iterations. One stakeholder suggests that someone should be responsible for developing and maintaining the product roadmap. Who should assume this responsibility?

  39. Question 39 of 161
    39. Question

    39. Which of the following elements are included in the business case? (Select three)

  40. Question 40 of 161
    40. Question

    40. A new project manager has just been assigned to oversee a stopped project. To quickly get accustomed to the project’s processes and understand the scope of work, which tool would be the most effective?

  41. Question 41 of 161
    41. Question

    41. Which of the following includes functional and non-functional requirements?

  42. Question 42 of 161
    42. Question

    42. Which tool or technique is part of defining acceptance criteria?

  43. Question 43 of 161
    43. Question

    43. A business analyst was assigned to an airline reservation system. The business analyst used the following artifact to illustrate the interactions with the system. What artifact did the business analyst use?

  44. Question 44 of 161
    44. Question

    44. A retail has recently experienced a 20% drop in online sales. What is the first step a business analyst would take?

  45. Question 45 of 161
    45. Question

    45. A product manager is pushing for the development of a new feature in an existing app. However, the business analyst has concerns that this feature may not address the core problem. What should the business analyst do next?

  46. Question 46 of 161
    46. Question

    46. A business analyst collected product sales data and compared them to the business objectives. What process did the business conduct?

  47. Question 47 of 161
    47. Question

    47. A business analyst is identifying the key problems and determining the necessary steps to move to a more efficient future state. Afterward, the business analyst will collaborate with stakeholders to ensure their concerns are addressed and obtain detailed information about their needs. These actions are part of which Business Analysis domains? (Select two)

  48. Question 48 of 161
    48. Question

    48. Which elicitation technique should be used when seeking in-depth information from subject matter experts?

  49. Question 49 of 161
    49. Question

    49. What skill enables a business analyst to leverage past experiences to make effective decisions when facing challenges?

  50. Question 50 of 161
    50. Question

    50. Which of the following responsibilities is unique to business analysis?

  51. Question 51 of 161
    51. Question

    51. A business analyst used the following model in analyzing product features from the viewpoint of the customer. What technique did the business analysis use?

  52. Question 52 of 161
    52. Question

    52. When the dimensions of the dug canals for the new dam project were compared to the plan, a significant variance was discovered. As a result, the project manager had to hold a meeting with the team to decide on the next steps. To which of the following process groups does the project manager’s activity belong?

  53. Question 53 of 161
    53. Question

    53. After creating the network diagram, the project manager identified three critical paths. What should the project manager do next?

  54. Question 54 of 161
    54. Question

    54. Which technique is used to develop the WBS?

  55. Question 55 of 161
    55. Question

    55. During a project status meeting, the project manager updated the sponsor on the project performance, indicating that the SPI is 0.75 and the CPI is 1.05. What does this imply?

  56. Question 56 of 161
    56. Question

    56. A Business Analyst is assigned to a Mobile App development project. One week prior to the product delivery date, the client requests a change to a specific business requirement. What should the Business Analyst do?

  57. Question 57 of 161
    57. Question

    57. During a project performance review meeting, a project manager presented the following figures: AC = $4,000, PV = $5,000, and EV = $5,500. What does that indicate about the project?

  58. Question 58 of 161
    58. Question

    58. The longest path in a network diagram is known as:

  59. Question 59 of 161
    59. Question

    59. A project manager is assigned to a 12-month project that has a $100,000 budget. Six months have passed and $60,000 has been spent. On closer inspection, the project manager finds out that so far, only 40% of the work has been completed. The value of the completed 40% work is referred to as:

  60. Question 60 of 161
    60. Question

    60. Which of the following statements are true about the deliverables of a predictive project? (Select two)

  61. Question 61 of 161
    61. Question

    61. Which of the following statements are true about the deliverables of a predictive project? (Select two)

  62. Question 62 of 161
    62. Question

    62. In the predictive approach, which of the following terms is used for both schedule and cost to define what you’ll measure against later in the monitoring and controlling phase?

  63. Question 63 of 161
    63. Question

    63. The diagram below depicts the decomposition of project deliverables into smaller tasks. This diagram is referred to as:

  64. Question 64 of 161
    64. Question

    64. The project SPI is 0.8, while the CPI is 1.1. What should be the project manager’s main concern?

  65. Question 65 of 161
    65. Question

    65. What should the project manager do to prevent scope creep and focus on fulfilling product requirements?

  66. Question 66 of 161
    66. Question

    66. A project manager is overseeing a project that has recently experienced inconsistent performance and a high defect rate. During a meeting, the sponsor asks where the project is currently standing, requesting an overview of work performance. Which of the following documents should the project manager send to the sponsor?

  67. Question 67 of 161
    67. Question

    67. What is Earned Value?

  68. Question 68 of 161
    68. Question

    68. What could be considered as the foundation for identifying current or future issues to support the decision of change requests?

  69. Question 69 of 161
    69. Question

    69. Which tool or technique is used to validate the scope of a project?

  70. Question 70 of 161
    70. Question

    70. Subdividing project deliverables and project work into smaller, more manageable parts is related to:

  71. Question 71 of 161
    71. Question

    71. A stakeholder expresses a need that was unknown to the project manager. Which stakeholder management process did the project manager likely skip?

  72. Question 72 of 161
    72. Question

    72. An activity has an Early Start (ES) of day 5, a Late Start (LS) of day 12, an Early Finish (EF) of day 10, and a Late Finish (LF) of day 17. Which of the following statements are correct regarding this activity? (Select two)

  73. Question 73 of 161
    73. Question

    73. Which process is conducted from the start to the finish of the project and is ultimately the responsibility of the project manager?

  74. Question 74 of 161
    74. Question

    74. During which process does a project manager confirm resource availability and obtain the team necessary to complete project activities?

  75. Question 75 of 161
    75. Question

    75. What performance measurement is used to assess the magnitude of variance in a project?

  76. Question 76 of 161
    76. Question

    76. A project manager calculates the early & late start and finish dates of a new project activity. One of the activities has the following representation. What is this activity’s float?

  77. Question 77 of 161
    77. Question

    77. The Agile triangle of constraints is different from the traditional triangle because it allows:

  78. Question 78 of 161
    78. Question

    78. An organization has decided to adopt the agile approach for its new project. What should they expect to get at the conclusion of the first sprint?

  79. Question 79 of 161
    79. Question

    79. In projects following the Scrum framework, which of the following questions won’t be asked to team members during daily stand-ups?

  80. Question 80 of 161
    80. Question

    80. The product owner and the project team are currently preparing and updating user stories for the next iterations. What activity does this depict?

  81. Question 81 of 161
    81. Question

    81. A project manager is facilitating a meeting with his project team and key stakeholders to prioritize all product backlog items based on their business value and risk level. Where should each category of items be placed in the product backlog? (from top to bottom)

  82. Question 82 of 161
    82. Question

    82. In an Agile project, how many members a project team should include?

  83. Question 83 of 161
    83. Question

    83. A project manager is choosing a development approach for a new project. Which of the following reasons would motivate the project manager to opt for an adaptive approach instead of a predictive one?

  84. Question 84 of 161
    84. Question

    84. Which of the following topics can be discussed in a retrospective meeting?

  85. Question 85 of 161
    85. Question

    85. In an agile development approach, what does a cross-functional team mean?

  86. Question 86 of 161
    86. Question

    86. During a sprint planning, a team member noticed that artifacts are missing, and the project manager asked the member to resolve the issue. What should the team member add? (Select two)

  87. Question 87 of 161
    87. Question

    87. One of the team members asks the project manager when a Sprint is considered completed. What should be the project manager’s response?

  88. Question 88 of 161
    88. Question

    88. Using an Agile approach, where should product requirements be documented?

  89. Question 89 of 161
    89. Question

    89. Typically, an agile scrum sprint is ____________ long.

  90. Question 90 of 161
    90. Question

    90. A cross-functional team should always make sure to focus on:

  91. Question 91 of 161
    91. Question

    91. What is the primary distinction between Agile and Scrum?

  92. Question 92 of 161
    92. Question

    92. The role of the product owner in an Agile project is: (Select two)

  93. Question 93 of 161
    93. Question

    93. A key stakeholder requested the project manager to urgently add a new user story to improve the product. How should the project manager respond to this request?

  94. Question 94 of 161
    94. Question

    94. To gauge each team member’s stance on a particular decision, a project manager uses the Fist of five voting technique. When the team starts voting, one member raises five fingers. What does this mean?

  95. Question 95 of 161
    95. Question

    95. In the graph below, what concepts or approaches correspond respectively to positions A, B, C, and D?

  96. Question 96 of 161
    96. Question

    96. What is a key element of delivering value early in Agile projects?

  97. Question 97 of 161
    97. Question

    97. What is a key factor that helps agile teams deliver at maximum speed?

  98. Question 98 of 161
    98. Question

    98. How does scope management in adaptive projects impact the creation of WBS?

  99. Question 99 of 161
    99. Question

    99. What is the key measure of progress in iteration-based agile?

  100. Question 100 of 161
    100. Question

    100. How is work-in-progress managed differently in flow-based agile compared to iteration-based agile?

  101. Question 101 of 161
    101. Question

    101. In which methodology does the team continuously work on the highest priority item, without the use of timeboxed iterations?

  102. Question 102 of 161
    102. Question

    102. In an interior design project for a library, the client asks the team to increase the number of bookshelves beyond what was agreed on. Since the project is on schedule and adding additional shelves will make no difference, the project manager consents to the client’s request. This is an example of:

  103. Question 103 of 161
    103. Question

    103. Which tool ensures that each solution requirement is linked to the business needs, goals, and objectives, as well as stakeholder expectations?

  104. Question 104 of 161
    104. Question

    104. A team, with no defined roles, uses a board and cards to categorize tasks into “To do”, “Doing”, and “Done”. Without too many restrictions, team members grab a card from the “To do” list and begin to work. What agile framework is being described?

  105. Question 105 of 161
    105. Question

    105. The stakeholder engagement process involves five steps. What is their logical sequencing according to the figure below?

  106. Question 106 of 161
    106. Question

    106. What is the purpose of a project charter?

  107. Question 107 of 161
    107. Question

    107. Before announcing the completion of the project execution, the project manager of a construction project reviews deliverables and performs a site walkthrough. What is the project manager performing in this scenario?

  108. Question 108 of 161
    108. Question

    108. In a project context, guidelines and policies are classified as:

  109. Question 109 of 161
    109. Question

    109. To compare the different suppliers and make the best choice, which of the following tools or techniques should the project manager use?

  110. Question 110 of 161
    110. Question

    110. The following are not a business analyst roles except:

  111. Question 111 of 161
    111. Question

    111. A project involves dozens of stakeholders. Most of them need high-level information and updates about the project status, while the rest need more detailed information and frequent updates. Therefore, the project manager decides to set up an action plan to respond to these different requirements. What should the project manager create?

  112. Question 112 of 161
    112. Question

    112. A project manager has been assigned to a 300 ft farm fencing project. Having previously managed two similar projects in another region, the project manager knows that the materials for a chain-link fence cost $10 per foot, while labor costs range from $10 to $15 per linear foot, depending on the workers’ experience and common rates in the region. What is the best way to estimate the labor cost per linear foot?

  113. Question 113 of 161
    113. Question

    113. A Business Analyst for a large construction project is working with the project manager to define the steps to perform stakeholder analysis. Which of the following correctly defines the steps for stakeholder analysis?

  114. Question 114 of 161
    114. Question

    114. A project manager was assigned to a large project that has unclear requirements and deliverables. After choosing an agile approach to deal with the situation, what should the project manager do next?

  115. Question 115 of 161
    115. Question

    115. A project manager who adopts a servant leadership style is onboarding a new team member. The project manager gives the team member a copy of the project charter and commits to sending them a copy of ________________, which covers team values, ground rules, and working agreements.

  116. Question 116 of 161
    116. Question

    116. A project has been hampered by many quality issues, putting the project at risk. Which meeting should the project manager conduct with the team to figure out how to avoid or deal with such problems in the future?

  117. Question 117 of 161
    117. Question

    117. During the project planning phase, stakeholders insisted that their conflicting requirements should all be considered and consolidated. That made it hard for the project manager to create a plan that satisfies all stakeholders. What should the project manager do to establish a common ground?

  118. Question 118 of 161
    118. Question

    118. Regardless of the type of development approach that a project manager adopts for their project, their top priority should always be:

  119. Question 119 of 161
    119. Question

    119. One year into managing a predictive project, and during the close project process, the project manager faces a key stakeholder’s refusal to sign off the deliverables due to non-compliance claims. What can the project manager do to ensure stakeholder acceptance?

  120. Question 120 of 161
    120. Question

    120. In a projectized organization structure, after getting the client’s approval of deliverables and officially closing the project, what should be the project manager’s next step?

  121. Question 121 of 161
    121. Question

    121. A project manager keeps receiving negative feedback concerning one of the project suppliers. The conflicts between the project team and the supplier’s team are getting worse recently and are starting to have a negative impact on the project. What should the project manager do next?

  122. Question 122 of 161
    122. Question

    122. For the next release, the product owner has selected a number of user stories totaling 110 points. Given that the team’s velocity is 20 story points, what’s the estimated duration to complete this release?

  123. Question 123 of 161
    123. Question

    123. The scope of business analysis is:

  124. Question 124 of 161
    124. Question

    124. Which of the below statements represents the most accurate definition of backlog refinement? (Select three)

  125. Question 125 of 161
    125. Question

    125. A company must select one of two projects that have the same budget, but different returns and risk levels. Which tool or technique should be used in order to make the right decision?

  126. Question 126 of 161
    126. Question

    126. What does “cycle time” mean?

  127. Question 127 of 161
    127. Question

    127. Which statement is true about the following chart?

  128. Question 128 of 161
    128. Question

    128. Working with the predictive approach, which of the following is most true?

  129. Question 129 of 161
    129. Question

    129. Before starting the project, the business analyst is classifying stakeholders according to their level of power, interest, and influence. This step is referred to as:

  130. Question 130 of 161
    130. Question

    130. Which of the following best describes business analysis?

  131. Question 131 of 161
    131. Question

    131. In a weak matrix organization, a project manager discovers that the assigned team lacks the necessary skills for the project. What should the project manager do next?

  132. Question 132 of 161
    132. Question

    132. A product owner who’s new to the agile approach wrote the following user story: “As a customer, I want a new functionality so that I can achieve a 50% increase in sales”. The project manager found the user story to be deficient, explaining to the product owner that:

  133. Question 133 of 161
    133. Question

    133. A product owner creates a release plan based on a projected team velocity of 50 story points. However, during the first two sprints, the team completed 37 points in sprint 1 and 35 story points in sprint 2. What should the agile project manager do in this situation? (Select two)

  134. Question 134 of 161
    134. Question

    134. A project team member notices that some requirements are missing from the project documentations. The project manager asks the team member to resolve the issue. What artifacts can the team member add to properly reflect the requirements statement? (Select three)

  135. Question 135 of 161
    135. Question

    135. Three manufacturing lines are producing 5 mm diameter cylindrical steel bars. In order to perform a quality inspection, the project manager takes 10 random bars from each line. The following are the inspection results in mm measurements. The results of Line 1 can be described as:

  136. Question 136 of 161
    136. Question

    136. A project manager is evaluating a potential industrial project. To determine whether its anticipated financial gains will outweigh its present-day investment, the project manager uses the Net Present Value (NPV) as an effective tool to help her determine whether the project will be profitable or not. For instance, NPV > 0 means:

  137. Question 137 of 161
    137. Question

    137. All of the following imply servant leadership characteristics, except:

  138. Question 138 of 161
    138. Question

    138. A project’s performance measurements are calculated based on the following information: EV = $2,000 and AC = $1,000. What is the status of the project?

  139. Question 139 of 161
    139. Question

    139. A project manager is developing the business case of a green transportation project. To do so, they decide to use the SWOT technique. How should the project manager apply this technique?

  140. Question 140 of 161
    140. Question

    140. The product owner should sort the product backlog items by placing:

  141. Question 141 of 161
    141. Question

    141. A project manager is leading a complex project with a very demanding sponsor who wants frequent updates on project progress and future plans. What’s the best way for the project manager to communicate with the sponsor?

  142. Question 142 of 161
    142. Question

    142. In a typical communication context, elements interfering with the transmission and understanding of the project manager’s message are called:

  143. Question 143 of 161
    143. Question

    143. Which of the following tools and techniques are used for stakeholders analysis? (Select two)

  144. Question 144 of 161
    144. Question

    144. A project manager is leading a one-year project. Five months into the execution phase, %50 of the project work is completed.

  145. Question 145 of 161
    145. Question

    145. During a workshop about the Agile approach, the project manager stated that Agile teams should be cross-functional and self-organizing, explaining that:

  146. Question 146 of 161
    146. Question

    146. A project manager plans to discuss with her manager the need for additional resources to handle complex tasks her team cannot perform. These resources will be released from the project once the tasks are completed. Which skills are most crucial for the project manager in this situation?

  147. Question 147 of 161
    147. Question

    147. To adopt an agile mindset, the project team can use all of the following questions while developing the product, except:

  148. Question 148 of 161
    148. Question

    148. A business analyst’s role involves extensive upfront planning and detailed requirements gathering primarily in the early stages of a project. In which development approach the business analyst is working?

  149. Question 149 of 161
    149. Question

    149. A project manager, who manages an online e-learning platform, decided to make all new release information accessible to the platform members under the “News” section on the website. What type of communication is the project manager intends to use?

  150. Question 150 of 161
    150. Question

    150. A project manager attended a leadership training workshop. The trainer listed the characteristics of servant leaders, then mentioned some examples of a servant leader’s behavioral traits, such as: (Select two)

  151. Question 151 of 161
    151. Question

    151. A project manager has just taken over an ongoing project for creating a newborns’ essentials brand. Items made of fabric are manufactured by external vendors. To get to know all vendors involved in the project, the project manager should check out:

  152. Question 152 of 161
    152. Question

    152. What are the areas of emotional intelligence (select three)

  153. Question 153 of 161
    153. Question

    153. A project manager is assigned to lead a megaproject that requires experts and resources from different countries. Unable to predict worldwide epidemics, the project team is worried about facing another event like CoronaVirus that might cause delays and cost overruns. What should the project manager do during the risk planning phase? (Select two)

  154. Question 154 of 161
    154. Question

    154. Which of these documents comprises thorough descriptions of work packages?

  155. Question 155 of 161
    155. Question

    155. Who can sign the project charter? (Select three)

  156. Question 156 of 161
    156. Question

    156. Knowledge garnered through personal experience is the most difficult to express, articulate, or write down. This type of knowledge is known as:

  157. Question 157 of 161
    157. Question

    157. What type of requirements are expressed in the form of a business case?

  158. Question 158 of 161
    158. Question

    158. How is the cost variance measured?

  159. Question 159 of 161
    159. Question

    159. Due to high levels of uncertainty, the project manager opts for the rolling wave method for the project planning. How is this method useful in this case?

  160. Question 160 of 161
    160. Question

    160. A project has 5 iteration cycles, as the project advances to the 3rd iteration, the number of user stories in the backlog decreases significantly. What’s the potential cause of the decrease?

  161. Question 161 of 161
    161. Question

    161. An agile project manager observes that several stakeholders have become disengaged; they rarely attend meetings or provide feedback and input. What can the project manager do to address this issue? (Select two)

About

Built for continuous growth, inspired by lifelong learning.
LearnLoop is a post-training learning hub automated by Edumation, designed exclusively for learners of Info Trek and Quorse.
It provides a space for participants to revise, refresh, and relearn what they’ve explored during training.

Our goal is simple: to help every learner turn training into lasting transformation through engaging, bite-sized content and continuous learning support.

  • Practice
  • Get Course Details

© 2026 Edumation

Scroll to top
  • Watch & Learn
    • Power BI Buddy
    • Office Buddy
      • Excel
      • Word
      • PowerPoint
    • Power Platform Buddy
    • IT Service Buddy
    • Agile Buddy
    • Project Management Buddy
    • UX Buddy
  • Practice
    • Check My Competency
    • Check My Exam Readiness
  • Get Course Details
Login
Accessing this course requires a login. Please enter your credentials below!

Lost Your Password?